Design, Supply and Installation of Mechanical, Electrical, Power and IT Equipment for Sopot, Sarlah and Bancarevo Tunnels, E80 Highway, Corridor X,
Republic of Serbia
2018 - 2019

Technical Parameters and work volumes:

Number of tunnels
3 double tube tunnels
Bancarevo
left tube 721 m,
right tube 705 m
Sopot
left tube 115 m,
right tube 115 m
Sarlah
left tube 465 m,
right tube 478 m

Employer: Koridori Srbije d.o.o. Belgrade, Kralja Petra 21, Serbia,
Contract duration: September 2018 – October 2019

The scope of works in this Project consists of design, supply and installation of the systems vital for traffic and tunnels functioning. Fire protection system; Telecommunication system; Traffic information system; Tunnel and Bridge lighting; Tunnel power supply; Tunnel ventilation system; Design of Control and Management Plans; Tunnel information system; Electronic communications network were installed and the latest technology for all systems has been applied.

The Corridor X, east section has been opened for traffic on November 9th, 2019.